Ruias-led Essar Steel plans to start the first
phase of production from its proposed USD 1.1
billion steel plant at Minnesota in the US by
2011, company sources said.
The activities being pursued by Essar Steel Minnesota
LLC (ESML), part of Essar Steel Holdings Ltd,
far enable the project to be on schedule and produce
iron ore pellets in 2011, they added.
"Since the ground break, Essar has accomplished
several milestones relating to the project such
as site survey, soil investigation, commencement
of de-watering of mine pits and site grading related
activities," Essar Steel Minnesota President
and CEO Madhu Vuppuluri said.
Besides iron ore mining and production, the proposed
project will have a 4-million tonne pellet plant,
a DRI (direct reduced iron) unit and steel making
facilities. In the second phase, a slab-making
unit would also come up.
The steel major plans to consume iron pellets
and other allied products from its Minnesota unit
for the Algoma plant in the US.
So far, the company has invested in the project
from its internal accruals, but is now looking
at finance options from institutions in Canada,
US and Europe.
"Essar does not fear the market risk for
its products, which makes ESML project financially
viable for banks to provide project finance,"
a senior company official said.
ESML is confident of securing financial tie-ups
for the project by end of the year and is believed
to be working out the details of the amount to
be borrowed. After getting environmental clearances
and acquiring over 8,000 acres, the company did
ground breaking for the project in September 2008.
It has already awarded multi-million dollar contracts
over the last one year for basic engineering works
and developing the site.
Essar had acquired Minnesota Steel in 2007 end
for an undisclosed amount. Post-merger, ESML is
endowed with long-term lease of over 1.4 billion
tonnes of iron ore resources that will support
both pellet and steel operations.
At full production, ESML will employ nearly 500
people and up to 2,000 construction workers over
the course of the project.
|